Our solar power system is now in operation
As of January 1st, 2026, we have commissioned our solar power system installed on the roof of one of our warehouse facilities. The project has been completed as part of our ongoing focus on responsible energy use and efficient operations.
The system has a total capacity of 601 kWp and consists of 1,352 solar panels installed on the warehouse building, covering approximately 3,200 m² of roof area. The system is fully integrated into the existing structure.
The expected annual electricity production is estimated at 571,156 kWh. The electricity generated is used directly in our daily operations and supports, among other things, our forklift fleet. Looking ahead, the electricity will also be able to supply charging stations planned for installation in 2026 for employees and visitors on site.
Any electricity consumption not covered by our own solar production is supplied as CO₂-neutral and renewable energy based on hydropower. This is documented through climate certificates from Norlys.
The project was completed in collaboration with external partners and forms a long-term part of our sustainability approach and responsible business practices.